NEW QUESTION 132
How are team managers involved in tailoring PRINCE2 suit the project?

  • A. Team managers should document the tailoring of the work packages
  • B. Team managers may advice on tailoring to improve the management of work packages
  • C. Team managers should not be involved in tailoring PRINCE2
  • D. Team managers are accountable for the tailoring of the work packages

Answer: B

 

NEW QUESTION 133
Where should a Team Manager look for information on the quality required for a product?

  • A. Product Description
  • B. Quality Management Strategy
  • C. Project Initiation Documentation
  • D. Team Plan

Answer: A

 

NEW QUESTION 134
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

  • A. project's cost tolerance
  • B. project's risk tolerance
  • C. change budget
  • D. project budget

Answer: D

 

NEW QUESTION 135
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

  • A. Checkpoint Report
  • B. Product Status Account
  • C. Highlight Report
  • D. Issue Report

Answer: D

 

NEW QUESTION 136
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.

  • A. the release of resources
  • B. the measurement of benefits NOT yet realized
  • C. the handover of products
  • D. open issues and risks

Answer: D

 

NEW QUESTION 137
Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

  • A. Change
  • B. Plans
  • C. Risk
  • D. Quality

Answer: C

 

NEW QUESTION 138
Which is one of the three levels of plan in PRINCE2?

  • A. Programme Plan
  • B. Project Brief
  • C. Team Plan
  • D. Benefits Review Plan

Answer: C

 

NEW QUESTION 139
Who is the key project decision-maker in the project management team?

  • A. Project Manager
  • B. Change Authority
  • C. Corporate management
  • D. Executive

Answer: D

 

NEW QUESTION 140
Which product describes the method the project will use to engage with corporate, programme management or the customer?

  • A. Communication management approach
  • B. Change control approach
  • C. Quality management approach
  • D. Benefits management approach

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 141
Which is a task of product-based planning?

  • A. Write the Project Product Description
  • B. Produce Product Status Accounts
  • C. Prepare the Work Packages
  • D. Identify activities and dependencies

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 142
If an informal issue is defined as a problem or concern, where should it first be recorded?

  • A. Daily Log
  • B. Risk Register
  • C. Issue Register
  • D. Exception Report

Answer: A

 

NEW QUESTION 143
When is the 'managing a stage boundary' process used?

  • A. Near the end of delivery stages
  • B. Immediately alter the project board has authorized the previous stage
  • C. Immediately after the project board has authorized the next stage
  • D. Near the end of each stage

Answer: A

 

NEW QUESTION 144
Why is a Project Brief produced?

  • A. To record the strategies andmanagement controls to be used by a project
  • B. To provide a full and firm foundation for the initiation of a project
  • C. To be used by the Project Board as a basis for reviewing the progress of a project
  • D. To act as a trigger for the Starting up a Project process

Answer: B

 

NEW QUESTION 145
How many tasks does the product-based planning technique describe?

  • A. Two
  • B. Three
  • C. Four
  • D. One

Answer: C

 

NEW QUESTION 146
What should be considered when defining the number of management stages in a project?

  • A. When key decisions need to be made
  • B. When project support will be available
  • C. When highlight reports will be submitted
  • D. When the team managers are available

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 147
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits

  • A. 2 and 3
  • B. 3 and 4
  • C. 1 and 4
  • D. 1 and 2

Answer: D

 

NEW QUESTION 148
Which is a purpose of the Risk theme?

  • A. Establish a method for the implementation of continuous improvement during the project
  • B. Provide the Project Board with a time-driven control to capture all project risks
  • C. Establish a cost-effective procedure to identify, assess and control risks
  • D. Identify, assess and control problems that have occurred

Answer: C

 

NEW QUESTION 149
......